Capacities
Capacities in the intraday system are provided by TSOs.
Cross-border capacities are handled implicitly, that means local order book views take into account capacities that are allocated by different TSOs on each border.
Cross-border trades will only be possible if there is enough allocated capacity between the areas.
Intraday capacities are determined by the relevant TSOs after flow results of the day-ahead auction.
Exact timing of capacity allocation varies and depends both, on operational procedures and individual agreements between TSOs on the different borders.
D=Delivery
*Exemptions to 15 minute products and their Gate Closing Times (GCT) due to local TSO limitations:
- SE: 60 minutes before delivery hour (Q1: GCT = 60 min, Q2: GCT=75 min, Q3: GCT=90 min, Q4: GCT=105 min).
- NO: 15 minute products are not available in Norway.
Capacity updates
Intraday capacities are updated automatically, depending on the volume and direction of intraday trades.
Capacities can further be changed directly by TSOs as a result of operational issues, e.g. an outage on a transmission line.
Ramping
As in the day-ahead auction, ramping restrictions apply in intraday.
As a result the entire remaining capacity after the day-ahead auction may not be available for the market on ramped connections.
A full description of ramping restrictions can be found here.